Mobile substation
Our mobile substation enables us to keep our customers' power on while we work.
The $2.2 million vehicle was built in Greymouth in 2019 and arrived in the North Island to start work on our electricity network in early 2020.
It allows us to bypass zone substations during planned maintenance and upgrades, which is more convenient for our customers as there are no planned outages to allow the work to go ahead.
From a safety perspective, using the mobile substation means our field crews no longer work near live equipment, and it removes the pressure to complete maintenance within a scheduled planned outage time.
Mobile substation snapshot
- Power bypasses zone substations and flows through the mobile
- Allows safe maintenance and installation work on zone substations
- No disruption during switching from normal supply to the mobile substation
- Eliminates the need for lengthy planned outages during substation work
- Can be deployed in the event of major unplanned substation faults
- Powerco maintains 115 zone substations on its network
- Mobile substation weighs 38 tonne and is 15.7m long
- Specifications allow unrestricted movement on New Zealand roads
- Engineered to withstand the shocks of road travel
- Trained team of contractors oversee each mobile installation
- Only takes a couple of days to set mobile up at most sites